Client – Muir Housing Group
Services Provided – Design & Contract Administration, Principal Designer, Q.S & Site Monitoring Services
Value – £470,000
Programme – 26 weeks
IGL were initially engaged to investigate and report on defects in the existing roof which had been experiencing significant water ingress since construction.
Following detailed investigations and opening up, IGL advised on suitable remedial measures, producing designs & specifications for the works.
Following the appointment of a contractor for the works, IGL undertook contract admin and detailed site monitoring of the works including cost control.
The detailed recording and production of a photographic defects log by IGL has enabled the Client to pursue a robust claim against the original developer.